Back in May 2004, plans were drawn up to relocate the 13th green. The fairway and tees were constructed in preparation for the new green, but unfortunately, the funds were never available to complete the project. Fast forward to 2026, and the Board has decided that we need to introduce a 19th hole to allow the club to commence our green resurfacing program. With the groundwork for the proposed 13th green already in place, the decision was made to put the 13th green where it was originally intended to go. This will provide the club with a number of benefits, including a spare green that can be used during the resurfacing program, as well as a full-length practice fairway for members.

Our Golf Course Manager Shaun reached out for recommendations on who could undertake the construction of the new green. We were given the name of Paul Gumbleton. After meeting with Paul, he put us in touch with Craig Parry, who has now provided us with the design for the new green.

The New 13th Green

The new green will be the largest green on the course, measuring approximately 605 square metres, compared with the existing 13th green, which is 586 square metres.

The additional size will provide us with:

• More pin placement options

• Greater flexibility in course setup

• Reduced wear and tear on individual areas of the green

• A more sustainable putting surface over the long term

Construction of the new green is scheduled to commence sometime in October 2026, weather permitting. Total Cost: $139,000

Why Are We Resurfacing Our Greens?

Over time, we have experienced significant couch grass encroachment, which has affected the quality of our putting surfaces and the overall health of the greens.

The resurfacing process will give us the opportunity to address these issues properly. As part of the work, the drainage and underlying profile beneath each green will be inspected and assessed, ensuring that any problems can be identified and addressed before the new surface is established.

The Long-Term Plan

The project will begin with the resurfacing of the putting green, which will become our nursery green. This will provide us with an important resource for growing and establishing turf to support the future resurfacing program. From there, the plan is to resurface approximately one to two greens each year, depending on weather, course conditions and available resources. This is a significant project for the club, but it is one that will provide long-term benefits for the quality and consistency of our greens, while also giving us greater flexibility during future maintenance and resurfacing works.

We look forward to keeping members updated as the project develops.